Client
Hutchinson Builders

Year
2018

Value
$10 million

Location
Palmerston

Download PDF

Gateway Shopping Centre Stage 2 comprised three buildings incorporating over 12,000m2 of net lettable area and 440 car parking bays.

ADG provided structural engineering service to Hutchinson Builders from concept design stage through to completion on site.

Gateway Shopping Centre Stage 2

Palmerston

Gateway Shopping Centre Stage 2 is constructed in precast concrete panels with steelwork roof. ADG worked closely with Hutchinson Builders on the steel design as all steel was imported and had to be designed to specific transport limits.

ADG’s value engineering approach to the structural design, particularly in relation to the cyclonic wind loads, provided a cost-effective structure maximising return for the client. Gateway Stage 2 Large Format Retail was delivered on time and within budget.