USFPI – Marine Rotational Force Darwin (MRF-D)
Interim Accommodation

 

ADG was engaged to provide the civil design (earthworks, pavements, stormwater drainage and footpaths), structural and temporary works design of the electrical substation

 

United States Force Posture Initiatives (USFPI) Modular Accommodation Project

Darwin

The site was contaminated with asbestos and thus a capping layer had to be placed over the site to make it safe for living. As the existing soil was contaminated with asbestos, trenching and excavation within the existing soil was a costly and slow exercise.

ADG provided unique design solutions for stormwater to minimise the inground infrastructure saving the client time with construction programme and significant cost reductions for minimal trenching works within asbestos contaminated material.

ADG civil design helped the client to excel the construction well ahead of program and finish the project on budget and ahead of schedule.