ADG's temporary works and construction services have provided design and advisory input to help enable the launch of the southern hemisphere's largest tunnel boring machines beneath Sydney Harbour.
Client
Acciona
Location
Birchgrove, Sydney
Sector
Transport Infrastructure
Partner
Transport for NSW
Services
Temporary Works Design, Construction Services, Independent Checking Engineer (ICE) Review

Beneath Birchgrove, ADG’s temporary works and construction services have supported one of Sydney’s most significant infrastructure undertakings by providing design and advisory input to help enable the launch of the southern hemisphere’s largest tunnel boring machines beneath Sydney Harbour.

The Western Harbour Tunnel, a $7.4 billion city-shaping project, required innovative temporary works designs to maintain safety and enable efficiency during TBM assembly within a confined underground environment. ADG collaborated closely with delivery partners to provide targeted design support and independent verification, integrating design expertise with construction know-how to achieve safe, efficient outcomes.

$7.4 B
BILLION

Project Value

15.7 M
DIAMETER

TBMs, the largest in the Southern Hemisphere

500
TONNE CRANE

Erected within TBM launch chambers

380 +
TBM COMPONENTS

Assembled underground

Critical Engineering Challenges

Steel Gantry Crane Runway Beam Design
Design of runway beams for 500-tonne and 60-tonne gantry cranes, essential infrastructure enabling the precise assembly of more than 380 TBM components within a confined underground launch chamber.

Reinforced Concrete Temporary Pavement Design
Design of approximately 400 metres of reinforced concrete temporary pavement within the tunnel, providing stability and access for construction activities.

Independent Checking Engineer (ICE) Review
ICE review of the TBM launch structure, providing assurance and strengthening confidence in this complex phase of works.

ADG's Solution

Drawing on extensive experience in temporary works and construction-phase services, ADG provided targeted design support and independent verification across critical elements of the TBM launch procedure. This included steel gantry crane runway beam design for the 500-tonne and 60-tonne cranes used to assemble TBM components, reinforced concrete temporary pavement extending around 400 metres of tunnel, and Independent Checking Engineer review of the TBM launch structure.

By integrating design expertise with construction know-how, ADG’s construction services team supported delivery partners to achieve safe, efficient outcomes.

Southern Hemisphere's Largest TBMs

ADG’s temporary works designs supported the assembly and launch of the southern hemisphere’s largest tunnel boring machines, each with a 15.7m diameter and a 462-tonne cutterhead, beneath Birchgrove, up to 50 metres below sea level.

TEMP WORKS FOR YOUR PROJECT

Let's start the conversation.

When critical assets can’t stop operating and the engineering margins are tight, you need the home advantage. Let’s talk about your next transport infrastructure challenge.

Meet the team or connect with your local ADG office.

Have a project in mind?

Related Projects

RAIL, TRANSPORT & INFRASTRUCTURE

Cross River Rail

The Inner Northern Busway carries thousands of commuters daily through Roma Street Station. When Cross River Rail's tunnel alignment passed directly beneath its foundations, the challenge was clear: protect critical infrastructure, maintain 24/7 operations, and deliver certainty to multiple government stakeholders. ADG developed a micropiled underpinning methodology that allowed tunnelling to proceed whilst the busway remained fully operational
Read more
Transport Infrastructure

Melbourne Metro Tunnel

ADG's bespoke cradle design delivered innovative temporary works solutions across 120+ work packages, enabling seamless tunnel boring machine retrieval and relaunch whilst maintaining construction schedules on Victoria's transformative $11 billion transport infrastructure project.
Read more
Morley-Ellenbrook Rail Project
TRANSPORT, INFRASTRUCTURE

Morley to Ellenbrook Line

ADG delivered comprehensive structural and civil engineering for Perth's transformative 21-kilometre Morley to Ellenbrook rail line, creating five new stations and connecting north-eastern communities through integrated alliance partnership and fast-tracked program delivery.
Read more