Location
Caboolture, Queensland
Client
Badge Constructions
Project timeline
Stage 1: 2019 – 2020
Stage 2: 2020 – 2021
Despite time constraints imposed to minimise disruptions to the school environment, ADG was able to efficiently deliver high level design and documentation for the client, and successfully coordinated with external consultants and design and construct contractors.
Caboolture, Queensland
Badge Constructions
Stage 1: 2019 – 2020
Stage 2: 2020 – 2021
Badge Construction required structural and civil engineering expertise to effectively and efficiently develop high-level design and documentation of multiple special purpose general learning buildings and suspended walkways for Caboolture Special School. Following the successful completion of this phase, design and documentation of the hall and classroom was also required.
ADG was engaged by Badge Construction to undertake structural and civil engineering services under a fast-tracked Design and Construct contract for the Caboolture Special School project. A major emphasis was placed on the timely deliverance and efficient design of the project, with ADG’s industry experience proving an excellent resource for developing innovative solutions to on site challenges.
Led by ADG Project Director Jeremy Cockram, services provided included:
Following the high-level, efficient design approach and construction solutions developed in Stage 1, ADG was further engaged to develop the design and documentation of the hall and classroom for Stage 2 of the project. The execution of these design stages resulted in a 10 per cent cost reduction against the estimated benchmark and ultimately, is a testament to ADG’s ability to deliver innovative, successful, timely and on budget solutions for their clients.
Several efficiencies were also developed throughout the project. ADG’s documentation of post-tensioned slabs usage contributed to construction efficiency, while the adoption of a jointless slab on ground for the hall further contributed to construction time savings. The custom designed prefabricated steel walkway structure also increased the speed of construction.